Venice Pier Refurbishment

Posted on 04/17/2019

PROPOSED PUBLIC ACCESS PLAN

Stage 1:  Pier is closed**, with no public access. Contractor will work on Approach. Closed September 2019  after Labor Day, estimated completion October 2019

Stage 2:  Pier is opened**, with public access* of full pier width, to Platform 11. Contractor will work on pier west of   Platform 11.  estimated completion November 2019

Stage 3:  Pier is opened**, with public access* of full pier width, to Platform 9. Contractor will work on pier west of Platform 9. estimated completion December 2020

Stage 4:  Pier is opened**, with public access* of full pier width, to Platform 7. Contractor will work on pier west of Platform 7. estimated completion January 2020

Stage 5:  Pier is opened**, with public access* of full pier width, to Platform 5. Contractor will work on pier west of Platform 5. estimated completion March 2020

Stage 6:  Pier is closed**, with no public access. Contractor will finish the balance of the pier repair. Grand Re-Opening upon completion. estimated completion May 2020 before Memorial Day

Please see attached PDF for more information.